CancelledStatus in the DLD project register · project no. 1313

Bay Central East Tower

Bay Central East Tower in Dubai Marina, Dubai: DLD project no. 1313, registered 2012, listed as cancelled in the DLD project register. Developer: Bay Central Developments Phase 2 Limited.
60.3%Completion recorded
16Planned units
3Floors
2012Registered with DLD
Arabian & Spainsh Tower (Phase 2), Al Hebiah Fourth: cancelled Dubai project (lowrise icon)
DLD status

Status and what it means

Bay Central East Tower is a real-estate project in Dubai Marina, Dubai, registered with the Dubai Land Department (DLD) as project number 1313 in 2012 by Bay Central Developments Phase 2 Limited.

The Dubai Land Department (DLD) project register lists the project as cancelled. DLD does not publish the date of the cancellation decision in its public records; the last inspection is the closest dated milestone. Once a project is cancelled, refund claims from its escrow account are handled through the special tribunal for the liquidation of cancelled real-estate projects in Dubai.

DLD inspections recorded completion of 60.3%. The structure was partially built before work stopped. It was planned with 16 units across 3 floors.

The facts on this page are taken from public DLD project records. They are not legal advice. If you bought a unit in this project, the recovery options depend on your contract, your payment history and the escrow position, which we assess case by case.

Project facts

AreaDubai Marina
DeveloperBay Central Developments Phase 2 Limited
DLD project number1313
DLD statusCancelled
LocationBay Central East Tower, Marsa Dubai
Registered with DLD6 March 2012
Construction start (planned)26 April 2012
Planned completion24 June 2013
Completion recorded60.3%
Units16
Floors3
Project area4,387 m²
Unit mix10 Shop · 6 Unspecified
Escrow bankDubai Islamic Bank (Public Joint Stock Company)
Timeline

Registration and inspection history

  1. Registered with DLD
  2. Planned construction start
  3. Planned completion

Status in the DLD project register: Cancelled. DLD does not publish the date of the cancellation decision; the last inspection is the closest dated milestone.

Location

Where the project is

Open in Google Maps · Plot coordinates from DLD records: 25.276987, 55.296249

DLD inspections

Site photos from DLD inspection records

If you bought a unit in Bay Central East Tower

  1. Gather your evidence. Sale and purchase agreement, all payment receipts, escrow deposit confirmations, and any correspondence with the developer.
  2. File your claim. Claims on a cancelled project are made through the special tribunal for liquidation of cancelled projects, which distributes the escrow balance and other recoverable assets among buyers.
  3. Get an assessment. Recovery depends on the escrow position, how much was built, and the developer's other assets. We assess this on a success-fee basis, with no upfront cost.
Investment recovery services Contact us
Questions

Frequently asked questions

Is Bay Central East Tower cancelled?

The Dubai Land Department project register lists Bay Central East Tower (DLD project no. 1313) with the status "Cancelled". DLD does not publish the date of the cancellation decision in its public records.

Who was the developer of Bay Central East Tower?

Bay Central East Tower was registered with DLD by Bay Central Developments Phase 2 Limited (developer no. 912).

Where is Bay Central East Tower located?

Bay Central East Tower is in Dubai Marina, Dubai. The DLD location record reads: Bay Central East Tower, Marsa Dubai.

How many units were planned in Bay Central East Tower?

DLD records list 16 units (10 Shop · 6 Unspecified) over 3 floors.

How much of Bay Central East Tower was built?

The latest DLD inspection recorded 60.3% completion.

Can buyers in Bay Central East Tower get their money back?

Buyers in cancelled Dubai projects can claim against the project's escrow account through the special tribunal for liquidation of cancelled projects. What is recoverable depends on the escrow balance, the amount built and the developer's other assets. Freehold Solutions assesses claims on a success-fee basis.

Freehold Solutions

Stuck in a cancelled or stalled Dubai project?

With Mohamed Alazazi Advocates & Legal Consultants we recover investments in cancelled projects on a success-fee basis. No upfront fees: we are paid only when you are.